Changing City: Tunneling ends on Kharghar-Turbhe Link Road, Navi Mumbai now set for quicker travel

In today’s episode of Changing City, brings you fresh developments on the Kharghar-Turbhe Link Road (KTLR), being constructed for better connectivity in Navi Mumbai. The tunnelling phase on the 5.9 km project has ended, bringing it one step closer to becoming a reality.
On June 29 and August 31, blasting and digging at both ends of the twin tunnels reached a breakthrough when they met in the middle, marking an end to the tunneling work. While much of the project is still underway, including elevated viaducts and road sections, the milestone brings Navi Mumbai closer to faster travel.
The tunnels were dug using the NATM method, blasting and digging through the rock because of their massive 18 m width.
Story continues below.
Subscribe to see fewer ads.
How it will help
The Kharghar-Turbhe Link Road, originating at the Juinagar railway station and diverging from the Sion Panvel Highway, runs straight through Navi Mumbai and Kharghar before reaching Central Park junction.
The tunnels were dug using the NATM method, blasting and digging through the rock because of their massive 18 m width.
The journey between the two points is 16 km long, running along the Sion Panvel Highway, Nerul and CBD Belapur, and then Kharghar, due to the vast mass of hills in between.
The Link Road, with its twin tunnels, cuts through it all to offer a quicker alternative, reducing a minimum 40-minute journey to just 10 minutes.
Officials said this would also reduce traffic on the Sion-Panvel Highway.
Story continues below this ad
Kharghar-Turbhe Link Road
Begins: Opposite Juinagar Railway Station on the Sion–Panvel Highway
Ends: Gurudwara Chowk/Central Park junction, Kharghar, near ACTREC
Length: 5.957 km
Twin tunnel lengths: 1.76 km
Breakthrough:
Tunnel 1 on June 29
Tunnel 2 on August 31
Tunneling done through: New Austrian Tunneling Method (NATM)
Lanes: 4 + 4
Cost: Rs 2,099 crore
Construction began: 2024
Deadline: December 2028
What’s left:
Contractor: Rithwik Projects Pvt. Ltd
Executing agency: CIDCO
“Achieving the breakthroughs of T1 on 29th June 2026 and T2 on 31st August 2026 marks a significant milestone in the Kharghar–Turbhe Tunnel Project. With both tunnels now successfully broken through, we have crossed a major engineering milestone and moved a step closer to delivering a safe, efficient and seamless connectivity link for Navi Mumbai. This achievement reflects the collective commitment, technical expertise and perseverance of everyone involved in the project. We are confident that the project will further strengthen connectivity and contribute significantly to the growth and development of Navi Mumbai,” said Ashwin Mudgal, VC and MD of CIDCO.