Govt races to avert Ganeshotsav traffic chaos on incomplete Mumbai-Goa highway

By Sohail Khan 4 September 2026, 7:54 am

MUMBAI: Ahead of the ten-day Ganesh festival, when thousands of migrants from Konkan go back to their native places, the Maharashtra government has stepped up preparations to manage the expected surge in traffic on the Mumbai-Goa highway

Published on: Sep 4, 2026, 07:54:20 IST

Prefer HTon Google

Share via
Copy link

    MUMBAI: Ahead of the ten-day Ganesh festival, when thousands of migrants from Konkan go back to their native places, the Maharashtra government has stepped up preparations to manage the expected surge in traffic on the Mumbai-Goa highway. It has directed the Public Works Department (PWD), National Highways Authority of India (NHAI), police and other agencies to work in close coordination to keep traffic smooth and uncongested.

    PWD minister Shivendrasinhraje Bhosale reviewed the traffic arrangements and the highway project at a meeting in Mahad, Raigad district. Even though the highway remains incomplete nearly 15 years after work began, Bhosale maintained that 90% to 95% was completed. “The Chiplun bypass will be opened for commuters after the monsoon, and we are planning to open the Mangaon bypass by January 2027,” he told reporters.

    Launched in 2011, the highway project has missed every single deadline set for its completion, including the latest one of March 2026. Envisaged as a dream corridor that would cut the Mumbai-Goa journey to around six hours, it remains a nightmare of unfinished stretches, construction bottlenecks and pothole-riddled roads. The 84-km Panvel-Indapur stretch is among the worst-affected sections.

    Bhosale directed officials to closely monitor traffic on the Nagothane flyover, particularly to ensure uninterrupted movement of light vehicles during the festival. Officials have been asked to take immediate corrective measures based on ground conditions and submit daily reports on traffic management. The minister also directed them to ensure that the Mangaon and Indapur bypass works were completed within their stipulated deadlines.

    However, the Panvel-Indapur stretch has exposed the government’s laxity in time management. Although Ganeshotsav begins on September 14, the NHAI plans to open the tender for repairs only on September 2. The entire tendering process, with its scrutiny of bids, award of the contract, signing of the agreement, submission of performance security and mobilisation of labour, machinery and materials, can only begin after the festival.

    The government is instead doing what it can on other fronts to ease the situation. Officials have been asked to identify and assess alternative routes to ease congestion. Internal roads that could be used as diversion routes are to be repaired and kept motorable before devotees set off for Konkan.

    Other plans to ease the discomfort of travellers include temporary facility centres at suitable locations along the highway which will provide drinking water, electricity, medical assistance and mobile toilets. Citing the large number of devotees travelling to Konkan, Bhosale said he would directly approach union road transport and highways minister Nitin Gadkari to pursue a toll waiver on the highway during Ganeshotsav.

    Catch every big hit, every wicket with Crickit, a one stop destination for Live Scores, Match Stats, Infographics & much more. Explore now!



    Stay updated with all the Breaking News and Latest News from Mumbai. Click here for comprehensive coverage of top Cities including Bengaluru, Delhi, Hyderabad, and more across India along with Stay informed on the latest happenings in World News.

    See Less

    Leave a Reply

    Your email address will not be published. Required fields are marked *