Business News›Industry›Transportation›Railways›From Rs 1 lakh crore to Rs 2 lakh crore: Mumbai-Ahmedabad bullet train cost doubles; Here’s what’s behind the massive rise
Read Today's Paper
From Rs 1 lakh crore to Rs 2 lakh crore: Mumbai-Ahmedabad bullet train cost doubles; Here’s what’s behind the massive rise
Synopsis
The cost of the Mumbai-Ahmedabad bullet train project has nearly doubled to Rs 2.1 lakh crore. The revised estimate was presented to the Cabinet for approval on Tuesday. Delays in land acquisition and the procurement of train sets have contributed to the significant cost escalation. The entire corridor is now expected to be completed by 2030, while a portion of the high-speed rail network is scheduled to become operational in August 2027.

Mumbai-Ahmedabad bullet train
The cost of the ambitious Mumbai-Ahmedabad bullet train project has been revised to around Rs 2.1 lakh crore, nearly double its original estimate of approximately Rs 1.1 lakh crore. The proposal seeking approval for the revised cost of the 508-km high-speed rail corridor was placed before the Cabinet on Tuesday, , citing sources.
The project has faced several delays since work began, with land acquisition, statutory clearances and delays in finalising the train sets contributing to the increase in both cost and completion timelines.
Mumbai-Ahmedabad bullet train project cost rises sharply
According to sources cited by , the Railway Ministry has attributed the latest cost escalation mainly to the time taken to acquire land in Maharashtra and delays in receiving the train sets from Japan.
The original estimated cost of the 508-km Mumbai-Ahmedabad High-Speed Rail Corridor was around Rs 1.1 lakh crore. The revised estimate of around Rs 2.1 lakh crore would represent an increase of nearly Rs 1 lakh crore.
Bullet train project likely to be completed by 2030
Sources told that the entire Mumbai-Ahmedabad bullet train corridor is now likely to be completed by 2030.
However, passengers could get to experience a portion of the high-speed rail network much earlier. The first leg of the corridor is scheduled to become operational in August 2027, according to the report.
The project connects Mumbai and Ahmedabad through a dedicated high-speed rail corridor and is expected to significantly reduce travel time between the two cities once fully operational.
Most additional funding may come from government support
The revised cost is also expected to change the project's funding structure. According to sources, most of the additional funding required for the increased project cost is likely to come through budgetary support.
The original Rs 1.1 lakh crore funding involved financial assistance from the Japan International Cooperation Agency (JICA) along with budgetary allocation.
The latest proposal therefore marks a significant increase in the financial commitment required to complete India's first bullet train corridor.
Bullet trains to be manufactured in India
Another major development concerns the trains themselves. According to sources cited by , the Railways has said that the high-speed trains will be manufactured in India.
Each train is expected to cost around Rs 390 crore to Rs 400 crore. The move towards domestic manufacturing is expected to play an important role as India builds capabilities for high-speed rail technology.
Why has the bullet train project faced delays?
The Mumbai-Ahmedabad bullet train project has experienced several challenges since it was announced.
Land acquisition, particularly in Maharashtra, took considerably longer than initially expected. The project has also faced delays related to statutory clearances and the finalisation and procurement of train sets.
These delays have pushed up project costs as construction and associated expenses have continued over a longer period.
In January, Railway Board Chairman Satish Kumar had said that the project cost had increased by around 83% to Rs 1.98 lakh crore.
No official Cabinet briefing yet
The proposal for the revised project cost was placed before the Cabinet meeting chaired by Prime Minister Narendra Modi on Tuesday, according to the report.
However, there was no official briefing on the decisions taken at the Cabinet meeting at the time of the report.
Add as a Reliable and Trusted News Source
Add Now!
(You can now subscribe to our WhatsApp channel)
(Catch all the Business News, Breaking News and Latest News Updates on The .)
…moreless
(You can now subscribe to our WhatsApp channel)
Read More News on
Mumbai Ahmedabad bullet trainMumbai Ahmedabad bullet train costbullet train project costMumbai Ahmedabad high speed railbullet train Indiabullet train cost Rs 2.1 lakh croreAhmedabad Mumbai bullet train projectbullet train project completion 2030bullet train first leg 2027Mumbai Ahmedabad high speed rail corridor
(Catch all the Business News, Breaking News and Latest News Updates on The .)
…moreless


Enter search text:
Continue reading with one of these options:
Limited Access
Free
Login to get access to some exclusive stories
& personalised newsletters
Login Now
Unlimited Access
Starting @ Rs120/month
Get access to exclusive stories, expert opinions &
in-depth stock reports
Subscribe Now
ET
Unlock Access to All Exclusives with ETPrime FREE TRIAL
15 Days Free: Unlock All ETPrime Exclusives, Market Tools & ePapers
Trial offer expiring in00 : 05 : 00
I'd rather pay ₹2599 now


Uh-oh! This is an exclusive story available for selected readers only.
Worry not. You’re just a step away.
Prime Account Detected!
It seems like you're already an ETPrime member with
Login using your ET Prime credentials to enjoy all member benefits
Log out of your current logged-in account and log in again using your ET Prime credentials to enjoy all member benefits.
Unlock ETPrime's Exclusive Stories Today!
Subscribe to gain powerful insights on business, stock market and industry trends.
Big Price Drop! Flat 40% Off
Student Only Offer
Already a Member? Sign In now
Already a Member? Sign In now
Already a Member? Sign In now
Offer Exclusively For You
Save up to Rs. 700/-
ON ET PRIME MEMBERSHIP
Avail Offer
Offer Exclusively For You
Get 1 Year Free
With 1 and 2-Year ET prime membership
Avail Offer
Offer Exclusively For You
Get 1 Year Free
With 1 and 2-Year ET prime membership
Avail Offer
Offer Exclusively For You
Get Flat 40% Off
Then ₹ 1749 for 1 year
Avail Offer
Offer Exclusively For You
ET Prime at ₹ 49 for 1 month
Then ₹ 1749 for 1 year
Avail Offer
Special Offer
Get flat 40% off on ETPrime
Avail Offer
Avail Offer
Claim NowAlready a Member? Sign In now
Need Assistance?
Connect with an ETPrime expert for personalized support and guidance
+91 9484700004
' + h3 + '
' + h4 + '
- ' + listing + '
What’s Included with
ETPrime Membership
1Exclusive Insights That Matter
Uncover the truth with our investigative stories
Make strategic moves using the real-world case studies
Read industry-specific stories to identify emerging trends
Spot opportunities with in-depth insights that matter
Trump temper on H-1B visas is forcing Indians to do these things to stay put in US

What Adani’s US indictment means for India Inc’s overseas fundraising
Why veterans like Reliance, L&T are on acquisition spree? Aswath Damodaran has an answer.

Will China’s dollar bond sale in Saudi Arabia trump the US in financial world?
Huawei launches its own OS to compete with Google and Apple. But can it win beyond China?

The problem with lab grown diamonds
Why a falling rupee is a better option for the economy

A list of top 20 momentum stocks that have delivered massive returns in one year
2Invest Wisely With Smart Market Tools & Investment Ideas
Alpha Trade
Get daily trade ideas from SEBI-registered research analysts.
Investment Ideas
Grow your wealth with stock ideas & sectoral trends.
Stock Reports Plus
All-in-one stock research with Stock Score, peer comparison & key signals.
BigBull Portfolio
Get to know where the market bulls are investing to identify the right stocks.
Stock Analyzer
Check the score based on the company's fundamentals, solvency, growth, risk & ownership to decide the right stocks.
Market Mood
Analyze the market sentiments & identify the trend reversal for strategic decisions.
Stock Talk Live at 9 AM Daily
Ask your stock queries & get assured replies by ET appointed, SEBI registered experts.
3Stay informed anytime, anywhere with ET ePaper
ePaper – Print View
Read the PDF version of ET newspaper. Download & access it offline anytime.
ePaper – Digital View
Read your daily newspaper in Digital View & get it delivered to your inbox everyday.
Wealth Edition
Manage your money efficiently with this weekly money management guide.
4Times Of India Subscription (1 Year)
ePaper
Read the PDF version of newspaper. Download & access it offline anytime.
Deep Explainers
Explore the In-depth explanation of complex topics for everyday life decisions.
Health+ Stories
Get fitter with daily health insights committed to your well-being.
Personal Finance+ Stories
Manage your wealth better with in-depth insights & updates on finance.
New York Times Exclusives
Stay globally informed with exclusive story from New York Times.
5Enjoy Complimentary Subscriptions From Top Brands
Docubay Subscription
Stream new documentaries from all across the world every day.
Stories you might be interested in




Leave a Reply